An unfinished ₱600-million convention center in Naga City has led the Philippine Anti-Corruption Czar (PACC), a private watchdog, to call for an investigation by the Office of the Ombudsman. The project, initiated in 2023 under former mayor Nelson Legacion, who served before Mayor Leni Robredo, remains unfinished despite receiving initial government funding, while its contractor has also been linked to the nationwide flood-control controversy.
The planned 5,000-person venue in Barangay Carolina originally carried an estimated construction period of two to three years. Centerways Construction and Development Inc. secured the ₱97.9-million first-phase contract in Jan. 2024.
During a Nov. 15 inspection, PACC representatives found rusting steel structures and vegetation surrounding the unfinished facility. Personnel from the National Bureau of Investigation and Department of Public Works and Highways (DPWH) joined the inspection.
A project engineer also reported the theft of steel materials during the construction suspension, raising further concerns about site security.
Centerways ranked among the country’s major flood-control contractors identified in 2025. The Department of Trade and Industry separately filed regulatory complaints against the company over alleged irregularities in flood-control projects.
Legacion, now Camarines Sur representative, denied corruption allegations, maintaining that the project was designed for phased construction. He said Phase 1, covering foundations and structural columns, was completed in April 2025.
Legacion attributed the stalled second phase to a DPWH location-tagging error that identified the project as being in Pili rather than Naga. He said another ₱100 million was allocated for Phase 2 in 2026.